Workers from Valley Precision Grading roll out some of the first pieces of field turf as construction at Wildcat Stadium Thursday at WIll C. Wood High School. The installation of the 57,600 square-feet of turf is expected to be completed by the end of February. Vacaville School District and Will C. Wood officials are still expected the $16 million stadium to be completed at the end of March or early April.